Production Schedule


Day 1- 19/05/2013

The bath scene which is the most difficult scene for the actress will be shot. This will take the longest out of all the scenes in the film so this will be the only scene shot.

Day 2- 26/05/2013

The rest of the film will be shot on this day as they aren't particularly challenging so I hope to get it all done in one day.

Shots:
- Looking in the mirror.
- Gazing out the window.
- Crying.
- Looking at reflection in water.

Day 3- 28/05/2013

I will be shooting the inserts for the film on this day, depending on the weather as I would like rain for this scene.

Shots:
- Rain fallin on the ground.
- Drops in water.
- Water moving.